Kulekhani Hydropower under maintenance mode     

The Kulekhani Hydropower Project has stopped generating power since Sunday, as it has begun carrying out maintenance work of the main gate valve and turbine of the second unit of the project.

“We have stopped generating power from the project for its maintenance,” said Sachidananda Mishra, chief of the project.

Mishra said that the first phase of maintenance of the project was completed recently.

A total of 92 MW of electricity is generated from both the units of the project. Of them, the first unit of the project produces 60 MW, while the second unit generates 32 MW. But at present, the project is generating around only about 50 per cent of the total capacity due to its damage.

He informed that three technicians, who have come from Japan, have started maintenance work of the second unit of the project.

According to him, the project will resume power generation only after 15 days.

“After completing the maintenance work, both projects will generate power as per their capacity,” he said.

With the start of maintenance of the project, the Nepal Electricity Authority (NEA) has revised its Load-Shedding Schedule to be effective from Monday. It has increased power outage period to 54 hours a week from 42 hours.


Bookmark/Share it:   

  • Delicious
  • Facebook
  • Reddit
  • StumbleUpon
  • Twitter
  • RSS Feed
  • Google
  • Digg
  • LinkedIn
  • Technorati



Related Posts :

  • The 92 MW Kulekhani Hydroelectricity Project resumed operation at full capacity from Wednesday after being in repair for a year resulting in reduced power output. The project had been generating only 46 MW for the last 11 months as the gen ...

  • The country’s largest hydropower project will stay shut for a week starting Monday. The closure of Mid-Marshyangdi Hydro Electricity Project is likely to add to the country’s power woes. According to project chief Mahendra Adhikari, Mid-Ma ...

  • At least one day a week will be load-shedding free, as the Nepal Electricity Authority is reducing the load-shedding hours from the present 35 hours a week to 12 hours from tomorrow. According to Nepal Electricity Authority, rise in water ...

  • The Nepal Electricity Authority (NEA) Monday decided to reduce load-shedding time to 35 hours from 54 hours per week. Dandapani Basyal, spokesperson of the NEA, informed that the new schedule will come into force from Tuesday. As per th ...

  • The foundation stone of 60-MW Upper Trishuli III ‘A’ was laid on Wednesday. With the country reeling under acute power crisis, the government is aiming at building the 60-MW project in three years. Laying the foundation stone of the projec ...

  • After remaining sluggish for four years, the construction of Kulekhani-III Hydropower Project has been moving ahead at a faster pace for the last three months. Over the three months alone, the project achieved 12 percent progress in the const ...

  • The Nepal Electricity Authority (NEA) signed power purchase agreements (PPAs) for a combined 361.55-MW electricity with 16 independent power producers (IPPs) in the first nine months of the current fiscal year. The state-owned power utilit ...

  • In an effort to contain the increasing power shortage, the Nepal Electricity Authority (NEA) brought diesel plants based in Duhabi of Sunari and Hetauda into operation on Tuesday. NEA, however, said the government’s financial support would d ...

  • Water level in the Kulekhani Reservoir that feeds two power projects—the 60-megawatt Kulekhani Hydropower Project (KHP)-I and the 32-megawatt KHP II—has gone up to the maximum level in four years. The water level in the reservoir, the only ...

  • The general public will heave a sigh of relief this festive season with the government planning to limit power cuts to just an hour a day during Dashain and Tihar. Officials said they have also worked out a plan to ensure “minimum loadshed ...

  • The rapid progress being made by the 456 MW Upper Tamakoshi hydropower project has encouraged the energy sector. The project did not shut down even during the Dashain holidays which has put stakeholders in a buoyant mood. Although most of the ...

  • Bangladesh wants to import 1,000 megawatts (MW) of power from a hydroelectric plant in Nepal, according to the reports from Bangladesh. A seven-member delegation led by Bangladeshi Prime Minister’s finance adviser Dr Moshiur Rahman visited ...

  • The Industrial Promotion Board has approved three projects that have collectively pledged investment worth around Rs 55 billion. The projects include a five star hotel promoted by MIT Group Holdings and two hydropower projects—Upper Trishuli- ...

  • Aims to complete the project by December 2019 Sixteen-year-old West Seti (750 MW) hydro project has got a new developer. The only reservoir project ready for construction located in the far west region will be developed by the China Three ...

  • Load-shedding hrs increased to 12 hours/day starting Dec 26,2012 Last Updated :  26th December  2012 | 11th Poush 2069  Nepal Electricity Authority has extended daily power cuts by two more hours. The power outage was earlier increased ...