
The preliminary inception report on the much-awaited Metro Railway in Kathmandu that was submitted to the Department of Railways (DoR) by consulting companies this week has outlined five lines for the network — four inside the Ring Road and one that will travel along the Ring Road.
The proposed 66.1-km network comprises 31 stations in total — including transfer and ordinary stations. The main terminal of the metro will be located at Ratnapark, says the report, which is yet to be approved by DoR.
According to the report, the 27.35-km Line 1–which follows the Ring Road–will connect different locations between Kalanki, Satdobato, Chabhil and back to Kalanki.
The Line comprises 18 stations including transfer points at Kalanki, Balkhu, Satdobato, Koteshore, Tinkune, Sinamangal, Chabhil, Narayan Gopal Chowk and Gongabu, from where passengers can change trains. Line 1 will have pick-up and drop stations at Ekantakuna, Dhobighat, Sitapaila Chowk, Swoyabhu, Balaju, Machhapokhari, Tilangatar, Dhumbarahi and Gwarko.
Those who want to go from Kalanki to Sinamangal can take trains on Line 2. This Line will have six stations in places ranging from Kalanki and Sanogaucharan to Sinamangal. The Line will pass through the main terminal.
The preliminary report shows that Line 3 will link Koteshwore and Gongabu. It will have eight stations in places like New Baneshwore, Singha Durbar and Thamel and will pass through the main terminal.
Similarly, Line 4, which is 11.5-km long, will connect Satdobato and Narayan Gopal Chwok, while Line 5 — the shortest at 8.4 kilometers — will link Balkhu and Chabhil.
According to Rajeshwar Man Singh, superintendent engineer at DoR, the Metro Railway will travel above ground in some places, underground in some areas and on the surface in selected places.
“But how it travels in each specific area will be decided after the complete feasibility report is prepared,” Singh said.
DoR has given the consulting companies until November to prepare the complete feasibility report.
The feasibility report of the project — which will be based on the preliminary inception report — will be prepared by Korea Transport Institution, Chungsuk Engineering Company, Kunwa Cunsulting and Engineering Company, Korea Rail Network Authority and two local companies– BDAnepal Private Limited and ERMC Private Limited. These companies were also involved in preparation of the preliminary inception report.
“We have paid around Rs 60.5 million (to the companies) to prepare the preliminary report and conduct the feasibility study,” Singh said.(Source:Republica)
The government is all set to approach the Asian Development Bank (ADB) for the preparation of a detailed project report (DPR) of a metro railway system and feasibility study of a North-South railway link. The Ministry of Physical Planning, ...
The government plans to select a firm to conduct a detailed project report (DPR) for the proposed Kathmandu Metro Railway Project within a week. The Investment Board (IB) has been assigned to implement the project. The Kathmandu Metro i ...
The government is set to start process of two railway projects from the beginning of the next fiscal year with a top priority on the railway construction. The Ministry of Physical Planning and Works began preliminary process on setting up ...
The impasse over the formation of a new government has stalled the feasibility study for a metro railway in the capital, an idea envisaged by the Ministry of Finance (MoF) to address its traffic woes. The concept of a metro railway in the ...
A high-level panel at the Ministry of Physical Planning and Works (MoPPW) has recommended Rites Limited (India) to conduct feasibility study of proposed East-West and Kathmandu-Pokhara electrical railway lines. A senior official at the MoP ...
Bardibas-Simara-Birgunj section to cost Rs 99 billion Construction of the Bardibas-Simara-Birgunj section of the proposed Mechi-Mahakali Electric Railway would cost a maximum of Rs 99 billion, according to a detailed project report (DPR) cur ...
The government is preparing to make the final decision on the track alignment of the Mechi-Mahakali Electric Railway very soon. Extending over 1,100 km, the cross-country railway will link Mahendranagar in the west with Kakkarbhitta in the ea ...
The government has kept the construction of the Mechi-Mahakali Railway in high priority considering the inevitability of the reliable development of roadway and railway for attaining long-term socio-economic prosperity in the country. The ...
Nepal will seek support from the South Korean government for the development of railway in the country. A high level government delegation led by the Minister for Physical Planning, Works and Transport Management, Hridayesh Tripathi, is sc ...
Decks have been cleared for the private sector to get into transmission lines construction. A board meeting of the Nepal Electricity Authority (NEA) on Monday decided to allow the private sector to invest in transmission line projects. Till ...
Nepal Purbadhar Bikas Company (NPBC) has said that it will start construction of a tunnel road linking Kathmandu-Kulekhani-Hetauda from February. The company added that a detailed project report (DPR) of the proposed road was at the final ...
The government has come up with an ambitious plan to reduce traffic jam woes of the Valley denizens. Department of Road has begun a feasibility study and survey on war-footing for what is said to be a first ever project of its kind. Engine ...
Landmark Worldwide Company Limited of South Korea has bagged the contract of conducting detailed feasibility study (DFS) of Nepal´s proposed second international airport at Nijgadh in Bara. Murari Bahadur Karki, joint secretary at the Mini ...
The Second International Airport (SIA) project has stirred back to life after 21 months in hibernation. The futuristic jet hub, which is planned to be built in Nijgadh, Bara in the Tarai plains, has regained government attention, and it has p ...
One in two Nepalis now has access to basic telecom services including mobile service. According to the Nepal Telecommunications Authority (NTA), tele-density has reached more than 50 percent from 1.47 percent a decade ago. The latest stati ...